ENI ACTIVITIES INTEGRATION - RAVENNA

… realization of 2 heavy “buried storage tanks” in a very compressible soil area …

ravenna.jpg

The project is related to the “ENI Activities Integration” for the construction of a new production plant of rubbers with polymerized styrene-butadiene composition to be installed into “area 18” of Versalis Production Plant in Ravenna.

The main design aspect were the foundations of 2 heavy “new buried storage tanks” (approximately 200.000 KN in an area 25x75 m for each tank) in an area characterized by very soft silty and clayey soil in a “normally consolidated” condition with groundwater at ground level.

Other design units were: 1) Foundations and structures of piperacks. 2) Concrete structures related to the extension of existing buildings. 3) General infrastructure works: Roads, squares and external paving works - all sewage networks (white, sanitary, black, chemical, oily) with the relative structures (wells, channels, drains, greens, etc.) including both new installations and restoration and connection with the various pre-existing sewer networks. 4) Site preparation works.

Andrea Antiga, as Soil’s Technical Director, signed the “detailed design” that was then used for works construction”.

OWNER

Versalis S.p.A. (formerly Polimeri Europa)

​

LOCATION

NORTHERN ITALY - Ravenna

​

YEAR

2010 - 2013

​

CLIENT

Andrea Antiga worked as Technical Director at SOIL S.r.l.

(TECNIMONT S.p.A. was the Soil’s Client)

​

PROJECT VALUE

7.8 Mio EUR.

​

TYPE OF WORK

Deep foundations, special geotechnical works, steel and concrete structures